Notice of Road Closure – Savannah!
April 19 – May 30, 2023
Mustang SUD will resume construction for infrastructure changes to existing sewer lines on Cherokee Rose Trail on Wednesday, April 19th!
Mustang SUD and their subcontractors will be conducting sewer work and connections for the Prose Prosper Apartments. This project, has been delayed due to an Atmos gas line in the area. Once complete, the concrete panels will be reopened to replace the temporary asphalt.
The construction will be in four phases. Each phase is expected to last approximately ten (10) days, weather permitting. The entire project duration is estimated to be 40 days.
Phase 1 Closures
April 19 – 29 (tentative) – Cherokee Rose at Fishtrap Road and access to the north alley of St. Simons

Phase 2 Closures
April 29 – May 9 (tentative) – Cherokee Rose from the south end of the St. Simons North alley to St. Simons

Phase 3 Closures
May 9 – 20 (tentative) – Cherokee Rose from the south side of St. Simons to the south side of the north Antebellum alley

Phase 4 Closures
May 20 – 30 (tentative) – Cherokee Rose from the south side of Antebellum Court north alley to the south side of Antebellum Court